10-14 Update

We are done painting until after the foyer tile has been installed. We are waiting to second coat the foyer until after that.

The painting is complete in the bathrooms and the cove base was installed. Most of the toilets are set and working.

The partitions were installed in the ladies room today! Yeah! The men’s room partitions were started and should be finished on Tuesday.

The staining of the baseboard is complete and men are planning to add the clear coat.

Light fixtures were cleaned and woodwork and banisters have all been wiped down.

We are hoping that the sound system work will be completed this week so that we can put the decking back on the platform by the end of the week.