9-30 Update

The cabinets for the kitchen, nursery, and bathrooms have all been ordered and could take approximately 4 weeks to arrive. The kitchen appliances were ordered and are available when we are.

The piano and organ were both looked at and seem to be okay! There doesn’t seem to be any permanent damage to either one. We are grateful!!

The “surviving” hymnals were wiped down on Monday.

Some work has been accomplished on the landscape islands. More work is scheduled for Monday evening (9-30).

The company that sells the bathroom dividers is coming on Tuesday. We are curious to know what the wait time will be on that important detail.

On Saturday we are planning to prime all of the new drywall to prepare it to be textured on Monday. The church will provide the primer and 9″ roller covers. Those who are willing to help are asked to bring paint pans, paint roller frames, and painting clothes. (The contractor said that we don’t need to trim with the primer so we will not need to brush the primer into the corners.)